Building the addition ... Phase
2 ... part 3
- July 31 ... the majority of the roof is on the main part of the
house. Major rain, wind and hail came through the area which cut
the day short.
- August 1 ... a slight change in plans. The siding and windows
that were supposed to arrive today (originally scheduled for a week
ago) have again been postponed until Friday. Due to that and the
rain scheduled for today, Mo went north to attend to things
there. Aaron stayed here and worked on a number of little things
that had to be done.
- August 2 & 3 ... Windows and siding did arrive Friday
morning. The porch went on and Mo and Aaron spent a couple of
days doing some necessary fine-tuning. There were some
issues with the level and plumb of the concrete walls, so a good deal
of shimming had to take place for the sheathing that the siding would
attach to on the lower level.
- August 6 ... Mo and Aaron finished up the sheathing and other
"fine-tuning" and by the end of the day there was house wrap
on part of the western side. They also got three windows in.
- August 7 ... A sailor would say we were on a full run today. The sails were
out and we had the wind at our backs and things really
got done. Butch and Matt joined Aaron and Mo so there were four
people working on the house. The only framing issue left was
with three windows that needed the openings re-framed. The rest of the house got wrapped,
almost all of the windows are in
and some of the siding went on.
- August 8 & 9 ... the past couple of days have been spent installing one more window and more
siding, as well as some soffit and fascia. The guys broke early
on Thursday to head north. A brother who now lives in California who
they haven't seen in about a year is home and the family is getting
together. All of the windows and most of the siding are on the
west side. Siding is on the upper section facing the road and
all but one window and part of the siding is on the east side.
There is even a section of the old part of the house that now has
insulation board and siding on it. We have reached a point where
we are now waiting on some materials that haven't yet come in.
Most of this should arrive by the end of next week so much of next
week's work will be on the heating and electrical inside.
- August 13 ... A crew from a tree contractor was here to look at the
three small trees by the front of the garage. When the
excavation was done, most of the roots on the west side were ripped
out. We were concerned that without the root network, those
trees wouldn't last long and were going to fall down in a good
wind. The contractor agreed. We were hoping that they
would top them and then we could cut them down, but they dropped all
three for us. We cut them up and removed the brush, gave the
wood away to neighbors and now have three less trees!
- August 13-16 ... A lot of work got done this week, but not all of it
immediately visible. Some siding was added, but we are in a
holding pattern waiting for more siding and corners. A lot of
the fascia and soffit was done and efforts shifted toward the inside
where most of the electrical boxes were mounted and much of the wiring
was run. On Thursday, we picked up the stone for the exterior
sections where that will be used. We also got the rest of the
bathroom accessories and all of the ceiling fans.
- August 21 ... Today started with a delivery from Barden. The
rest of the siding, corners, fire-rated doors and all of the interior
trim were on the load. We have suspended outside work to focus
on the interior to get ready for the sheetrock finisher/painter.
- August 22 ... As things progressed on the electrical work, today was
a big day. The electrical inspector gave the green light on all
of the wiring. He indicated that he only needs to come back one
more time to see everything in operation. The code officer also
gave us the go-ahead. Insulation and sheetrock went up in the
afternoon. By the end of the day, which was a late one, most of
the insulation was in the upstairs and much of the upstairs ceilings
and some of the walls were sheetrocked.
- August 23 & 24 ... Things continued on the inside.
Electrical wiring, wiring for TVs and computers, heat tubes, plumbing,
insulation and more drywall were all on the agenda. The garage
door contractor arrived Friday morning and started to install those,
but found that he had been sent the wrong hardware. Hopefully
the right stuff will come on Monday and he can continue on that.
- August 27 ... By the end of the day, all of the wiring had been run
in the living area, 98% of the drywall was up and some work had begun
in the lower area. The garage door contractor was also here this
afternoon and finished installing both doors. He will be back
after the finishing work is done to install the openers and keyless
entry system.
Go to page 4
Hover on any of the thumbnails and a larger image will appear. Do
not click on the thumbnails. That will take you to a new page with
just the picture and slow things down!
|