Building the addition ... Phase
1 ... part 3
- July 3 ... P & M came back and finished preparation of the
garage floor ... a tree crew contractor for National Grid (Asplundh) was also
here cutting trees to make way for the relocating of the neighbor's
entrance wire
- July 5 ... Barksdale Construction was here and put down the heating
tubes for the garage floor
- July 9 ... National Grid was here and installed a new pole on our
line with Hansons and re-routed their supply feed
- July 10 ... P & M poured the garage floor
- July 11 ... Asplundh tree crew was here and did some more trimming
On to the
building phase